The council has approved a contractor to rebuild the Ivatt Place playground on the West Kensington estate for all ages. No firms bid for the job, so it was awarded directly.
The playground at Ivatt Place on the West Kensington estate is to be rebuilt for children of all ages. Hammersmith and Fulham Council has signed off a contractor for the work after an open tender drew no bids at all.
The council’s executive director of place approved the decision on 25 November. It comes into force on 1 December unless councillors call it in by 30 November.
What the new playground includes
The officers’ report says the scheme will bring:
- natural play equipment for children of different ages and abilities, built from large timber logs on steel supports
- table tennis tables, benches and seating logs
- a planted route through the playground, with new trees, shrubs and grasses
- festoon lights and Gobo lighting fixed to the existing lamp posts, to make the space feel safer after dark
- the games courts (the MUGA) cleaned and repainted
- better paths and signs
Two slides from the existing playground will be reused, and the existing trees stay. Five “wildlife logs” are designed for play and, over time, as homes for insects.
Why it is being rebuilt
Residents told the council the current playground is “tired, mainly suited to young children, and locked at weekends”, the report says. They asked for a space that is “exciting, more dynamic, and used by all ages”.
The design was shaped with pupils at Avonmore Primary School and Normand Croft Community School, the tenants and residents’ association, the community garden group and W14 Youth Club. The youth club workshop used the Make Space for Girls approach, so that girls’ views on play were heard.
No bids, so a direct award
The council first advertised the contract on the open market after approval in April 2026. 37 suppliers registered an interest, but none bid by the deadline. The report says firms blamed the summer timing, a lack of capacity, confusion over the design and fabrication work, and the job falling outside their usual work.
Officers rejected re-advertising it, saying there was no sign the result would change. They recommended a direct award to a London-based small business that had not taken part in the tender. The firm is not named, and the contract value sits in an appendix kept private for commercial reasons.
The report says the price was checked against the council’s own cost estimate before the tender. The work is paid for by a grant from the Earl’s Court Development Company. It is the first project in a wider programme of public space improvements on the West Kensington and Gibbs Green estates, funded under an agreement between the developer and the council.
What it means for you
The contract is expected to last about 20 weeks, including design, building and handover. The report’s timetable, drawn up before the decision was signed, put the end date at 31 March 2027. An independent safety inspection must be passed before the playground reopens.
While it is shut, the council’s equality assessment points families to the play area at Gibbs Green and to Normand Croft Park, and says pop-up play sessions are being considered.
The contractor will also be asked to run a community planting day with residents and local schools. Most of the play equipment will be made off site, which the report says means fewer deliveries and less noise for neighbours.